Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

A.
Direct and Manage Project Work
Answers
A.
Direct and Manage Project Work
B.
Develop Project Management Plan
Answers
B.
Develop Project Management Plan
C.
Plan Quality Management
Answers
C.
Plan Quality Management
D.
Monitor and Control Project Work
Answers
D.
Monitor and Control Project Work
Suggested answer: B