Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

A.
Stakeholder register
Answers
A.
Stakeholder register
B.
Scope management plan
Answers
B.
Scope management plan
C.
Stakeholder management plan
Answers
C.
Stakeholder management plan
D.
Project charter
Answers
D.
Project charter
Suggested answer: A