Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

A.
Plan Procurement Management
Answers
A.
Plan Procurement Management
B.
Control Procurements
Answers
B.
Control Procurements
C.
Collect Requirements
Answers
C.
Collect Requirements
D.
Plan Cost Management
Answers
D.
Plan Cost Management
Suggested answer: A