The process of identifying and documenting relationships among the project activities is known as:

A.
Control Schedule.
Answers
A.
Control Schedule.
B.
Sequence Activities.
Answers
B.
Sequence Activities.
C.
Define Activities.
Answers
C.
Define Activities.
D.
Develop Schedule.
Answers
D.
Develop Schedule.
Suggested answer: B