Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

A.
Enterprise environmental factors
Answers
A.
Enterprise environmental factors
B.
Work performance reports
Answers
B.
Work performance reports
C.
Organizational process assets
Answers
C.
Organizational process assets
D.
Context diagrams
Answers
D.
Context diagrams
Suggested answer: A