Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

A.
Earned value management.
Answers
A.
Earned value management.
B.
Enterprise environmental factors.
Answers
B.
Enterprise environmental factors.
C.
Organizational process assets.
Answers
C.
Organizational process assets.
D.
Work performance information.
Answers
D.
Work performance information.
Suggested answer: D