Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

A.
Organizational process updates
Answers
A.
Organizational process updates
B.
Quality metrics
Answers
B.
Quality metrics
C.
Change requests
Answers
C.
Change requests
D.
Quality control measurements
Answers
D.
Quality control measurements
Suggested answer: B