Question 122 - CAPM discussion
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
A.
Urgent information need
B.
Sensitivity of information
C.
Project environment
D.
Ease of use
Your answer: