ExamGecko
Home Home / PMI / CAPM
Question list
Search
Search

Question 130 - CAPM discussion

Report
Export

In a project, total float measures the:

A.
Ability to shuffle schedule activities to lessen the duration of the project.
Answers
A.
Ability to shuffle schedule activities to lessen the duration of the project.
B.
Amount of time an activity can be extended or delayed without altering the project finish date.
Answers
B.
Amount of time an activity can be extended or delayed without altering the project finish date.
C.
Cost expended to restore order to the project schedule after crashing the schedule.
Answers
C.
Cost expended to restore order to the project schedule after crashing the schedule.
D.
Estimate of the total resources needed for the project after performing a forward pass.
Answers
D.
Estimate of the total resources needed for the project after performing a forward pass.
Suggested answer: B
asked 23/09/2024
Dean Pillay
47 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first