Question 131 - CAPM discussion
Which Knowledge Areas include processes from the Closing Process Group?
A.
Project Quality Management and Project Time Management
B.
Project Scope Management and Project Risk Management
C.
Project Stakeholder Management and Project Cost Management
D.
Project Integration Management and Project Procurement Management