Which Knowledge Areas include processes from the Closing Process Group?

A.
Project Quality Management and Project Time Management
Answers
A.
Project Quality Management and Project Time Management
B.
Project Scope Management and Project Risk Management
Answers
B.
Project Scope Management and Project Risk Management
C.
Project Stakeholder Management and Project Cost Management
Answers
C.
Project Stakeholder Management and Project Cost Management
D.
Project Integration Management and Project Procurement Management
Answers
D.
Project Integration Management and Project Procurement Management
Suggested answer: D