Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

A.
Project document updates
Answers
A.
Project document updates
B.
Activity list
Answers
B.
Activity list
C.
Activity attributes
Answers
C.
Activity attributes
D.
Project calendars
Answers
D.
Project calendars
Suggested answer: C