An input to the Identify Stakeholders process is:

A.
The project management plan.
Answers
A.
The project management plan.
B.
The stakeholder register.
Answers
B.
The stakeholder register.
C.
Procurement documents.
Answers
C.
Procurement documents.
D.
Stakeholder analysis.
Answers
D.
Stakeholder analysis.
Suggested answer: C