What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

A.
$50
Answers
A.
$50
B.
$100
Answers
B.
$100
C.
$125
Answers
C.
$125
D.
$175
Answers
D.
$175
Suggested answer: C