The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

A.
Project management plan.
Answers
A.
Project management plan.
B.
Project charter.
Answers
B.
Project charter.
C.
Work breakdown structure.
Answers
C.
Work breakdown structure.
D.
Stakeholder register.
Answers
D.
Stakeholder register.
Suggested answer: B