Which Process Group and Knowledge Area include the Sequence Activities process?

A.
Executing Process Group and Project Time Management
Answers
A.
Executing Process Group and Project Time Management
B.
Executing Process Group and Project Cost Management
Answers
B.
Executing Process Group and Project Cost Management
C.
Planning Process Group and Project Time Management
Answers
C.
Planning Process Group and Project Time Management
D.
Planning Process Group and Project Cost Management
Answers
D.
Planning Process Group and Project Cost Management
Suggested answer: C