Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

A.
Verified deliverables.
Answers
A.
Verified deliverables.
B.
Validated deliverables.
Answers
B.
Validated deliverables.
C.
Acceptance criteria.
Answers
C.
Acceptance criteria.
D.
Activity resource requirements.
Answers
D.
Activity resource requirements.
Suggested answer: A