An output of the Perform Integrated Change Control process is:

A.
Deliverables.
Answers
A.
Deliverables.
B.
Validated changes.
Answers
B.
Validated changes.
C.
The change log.
Answers
C.
The change log.
D.
The requirements traceability matrix.
Answers
D.
The requirements traceability matrix.
Suggested answer: C