During which process does the project team receive bids and proposals?

A.
Conduct Procurements
Answers
A.
Conduct Procurements
B.
Plan Procurements
Answers
B.
Plan Procurements
C.
Estimate Costs
Answers
C.
Estimate Costs
D.
Control Budget
Answers
D.
Control Budget
Suggested answer: A