The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

A.
Validate Scope.
Answers
A.
Validate Scope.
B.
Plan Scope Management.
Answers
B.
Plan Scope Management.
C.
Control Scope.
Answers
C.
Control Scope.
D.
Define Scope.
Answers
D.
Define Scope.
Suggested answer: C