Which output is the approved version of the time-phased project budget?

A.
Resource calendar
Answers
A.
Resource calendar
B.
Scope baseline
Answers
B.
Scope baseline
C.
Trend analysis
Answers
C.
Trend analysis
D.
Cost baseline
Answers
D.
Cost baseline
Suggested answer: D