The purpose of the Project Communications Management Knowledge Area is to:

A.
Monitor and control communications throughout the entire project life cycle.
Answers
A.
Monitor and control communications throughout the entire project life cycle.
B.
Maintain an optimal flow of information among all project participants.
Answers
B.
Maintain an optimal flow of information among all project participants.
C.
Develop an appropriate approach for project communications.
Answers
C.
Develop an appropriate approach for project communications.
D.
Ensure timely and appropriate collection of project information.
Answers
D.
Ensure timely and appropriate collection of project information.
Suggested answer: D