Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:

A.
Level of control.
Answers
A.
Level of control.
B.
Communication channels.
Answers
B.
Communication channels.
C.
Scope.
Answers
C.
Scope.
D.
Strategic alignment.
Answers
D.
Strategic alignment.
Suggested answer: A