Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

A.
Update
Answers
A.
Update
B.
Preventive action
Answers
B.
Preventive action
C.
Defect repair
Answers
C.
Defect repair
D.
Corrective action
Answers
D.
Corrective action
Suggested answer: D