Question 191 - CAPM discussion

Report
Export

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

A.
100
Answers
A.
100
B.
120
Answers
B.
120
C.
1,000
Answers
C.
1,000
D.
1,200
Answers
D.
1,200
Suggested answer: A