A project manager should communicate to stakeholders about resolved project issues by updating the:

A.
project records
Answers
A.
project records
B.
project reports
Answers
B.
project reports
C.
stakeholder notifications
Answers
C.
stakeholder notifications
D.
stakeholder register
Answers
D.
stakeholder register
Suggested answer: C