Which Project Time Management process includes bottom-up estimating as a tool or technique?

A.
Estimate Activity Resources
Answers
A.
Estimate Activity Resources
B.
Sequence Activities
Answers
B.
Sequence Activities
C.
Estimate Activity Durations
Answers
C.
Estimate Activity Durations
D.
Develop Schedule
Answers
D.
Develop Schedule
Suggested answer: A