Progressively elaborating high-level information into detailed plans is performed by the:

A.
project management office
Answers
A.
project management office
B.
portfolio manager
Answers
B.
portfolio manager
C.
program manager
Answers
C.
program manager
D.
project manager
Answers
D.
project manager
Suggested answer: D