A risk that arises as a direct result of implementing a risk response is called a:

A.
contingent risk
Answers
A.
contingent risk
B.
residual risk
Answers
B.
residual risk
C.
potential risk
Answers
C.
potential risk
D.
secondary risk
Answers
D.
secondary risk
Suggested answer: D