Question 218 - CAPM discussion

Report
Export

The purpose of developing a project scope management plan is to:

A.
Manage the timely completion of the project.
Answers
A.
Manage the timely completion of the project.
B.
Ensure that the project includes all of the work required.
Answers
B.
Ensure that the project includes all of the work required.
C.
Make sure the project will satisfy the needs for which it was begun.
Answers
C.
Make sure the project will satisfy the needs for which it was begun.
D.
Reduce the risk of negative events in the project.
Answers
D.
Reduce the risk of negative events in the project.
Suggested answer: B