A tool and technique used in the Develop Project Charter process is:

A.
change control tools
Answers
A.
change control tools
B.
expert judgment
Answers
B.
expert judgment
C.
meetings
Answers
C.
meetings
D.
analytical techniques
Answers
D.
analytical techniques
Suggested answer: B