A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

A.
risk management plan
Answers
A.
risk management plan
B.
human resource management plan
Answers
B.
human resource management plan
C.
scope management plan
Answers
C.
scope management plan
D.
procurement management plan
Answers
D.
procurement management plan
Suggested answer: D