A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

A.
cultural differences of team members
Answers
A.
cultural differences of team members
B.
possibility of communication misunderstandings
Answers
B.
possibility of communication misunderstandings
C.
costs associated with travel
Answers
C.
costs associated with travel
D.
costs associated with technology
Answers
D.
costs associated with technology
Suggested answer: C