Whose approval may be required for change requests after change control board (CCB) approval?

A.
Functional managers
Answers
A.
Functional managers
B.
Business partners
Answers
B.
Business partners
C.
Customers or sponsors
Answers
C.
Customers or sponsors
D.
Subject matter experts
Answers
D.
Subject matter experts
Suggested answer: C