The primary benefit of the Plan Schedule Management process is that it:

A.
provides guidance to identify time or schedule challenges within the project.
Answers
A.
provides guidance to identify time or schedule challenges within the project.
B.
tightly links processes to create a seamless project schedule.
Answers
B.
tightly links processes to create a seamless project schedule.
C.
guides how the project schedule will be managed throughout the project.
Answers
C.
guides how the project schedule will be managed throughout the project.
D.
creates an overview of all activities broken down into manageable subsections.
Answers
D.
creates an overview of all activities broken down into manageable subsections.
Suggested answer: C