The primary benefit of the Plan Schedule Management process is that it:
A.
provides guidance to identify time or schedule challenges within the project.
B.
tightly links processes to create a seamless project schedule.
C.
guides how the project schedule will be managed throughout the project.
D.
creates an overview of all activities broken down into manageable subsections.