Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?

A.
Program
Answers
A.
Program
B.
Functional
Answers
B.
Functional
C.
Project
Answers
C.
Project
D.
Portfolio
Answers
D.
Portfolio
Suggested answer: C