The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

A.
Methodology
Answers
A.
Methodology
B.
Risk category
Answers
B.
Risk category
C.
Risk attitude
Answers
C.
Risk attitude
D.
Assumption analysis
Answers
D.
Assumption analysis
Suggested answer: A