Which document includes the project scope, major deliverables, assumptions, and constraints?

A.
Project charter
Answers
A.
Project charter
B.
Project scope statement
Answers
B.
Project scope statement
C.
Scope management plan
Answers
C.
Scope management plan
D.
Project document updates
Answers
D.
Project document updates
Suggested answer: B