When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

A.
Bottom-up
Answers
A.
Bottom-up
B.
Parametric
Answers
B.
Parametric
C.
Analogous
Answers
C.
Analogous
D.
Three-point
Answers
D.
Three-point
Suggested answer: A