Question 318 - CAPM discussion
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
A.
Bottom-up
B.
Parametric
C.
Analogous
D.
Three-point
Your answer: