Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

A.
Cost management plan
Answers
A.
Cost management plan
B.
Quality management plan
Answers
B.
Quality management plan
C.
Communications management plan
Answers
C.
Communications management plan
D.
Risk management plan
Answers
D.
Risk management plan
Suggested answer: D