Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

A.
Organizational process assets
Answers
A.
Organizational process assets
B.
A work breakdown structure
Answers
B.
A work breakdown structure
C.
The project management plan
Answers
C.
The project management plan
D.
Enterprise environmental factors
Answers
D.
Enterprise environmental factors
Suggested answer: A