What is an objective of the Develop Project Team process?

A.
Feelings of trust and improved cohesiveness
Answers
A.
Feelings of trust and improved cohesiveness
B.
Ground rules for interaction
Answers
B.
Ground rules for interaction
C.
Enhanced resource availability
Answers
C.
Enhanced resource availability
D.
Functional managers becoming more involved
Answers
D.
Functional managers becoming more involved
Suggested answer: A