The product scope description is used to:

A.
Gain stakeholders' support for the project.
Answers
A.
Gain stakeholders' support for the project.
B.
Progressively elaborate the characteristics of the product, service, or result.
Answers
B.
Progressively elaborate the characteristics of the product, service, or result.
C.
Describe the project in great detail.
Answers
C.
Describe the project in great detail.
D.
Define the process and criteria for accepting a completed product, service, or result.
Answers
D.
Define the process and criteria for accepting a completed product, service, or result.
Suggested answer: B