Which schedule network analysis technique modifies the project schedule to account for limited resources?

A.
Human resource planning
Answers
A.
Human resource planning
B.
Fast tracking
Answers
B.
Fast tracking
C.
Critical chain method
Answers
C.
Critical chain method
D.
Rolling wave planning
Answers
D.
Rolling wave planning
Suggested answer: C