Which of the following is an output of the Monitor and Control Project Work process?

A.
Change requests
Answers
A.
Change requests
B.
Performance reports
Answers
B.
Performance reports
C.
Organizational process assets
Answers
C.
Organizational process assets
D.
Project management plan
Answers
D.
Project management plan
Suggested answer: A