Which action should a project manager take to ensure that the project management plan is effective and current?

A.
Conduct periodic project performance reviews.
Answers
A.
Conduct periodic project performance reviews.
B.
Identify quality project standards.
Answers
B.
Identify quality project standards.
C.
Follow ISO 9000 quality standards.
Answers
C.
Follow ISO 9000 quality standards.
D.
Complete the quality control checklist.
Answers
D.
Complete the quality control checklist.
Suggested answer: A