While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

A.
Utilize the change control process.
Answers
A.
Utilize the change control process.
B.
Crash the schedule to fix the defect.
Answers
B.
Crash the schedule to fix the defect.
C.
Leave the defect in and work around it.
Answers
C.
Leave the defect in and work around it.
D.
Fast-track the remaining development.
Answers
D.
Fast-track the remaining development.
Suggested answer: A