Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

A.
Collect Requirements
Answers
A.
Collect Requirements
B.
Direct and Manage Project Execution
Answers
B.
Direct and Manage Project Execution
C.
Monitor and Control Project Work
Answers
C.
Monitor and Control Project Work
D.
Develop Project Management Plan
Answers
D.
Develop Project Management Plan
Suggested answer: D