Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.
Initiating
Answers
A.
Initiating
B.
Monitoring and Controlling
Answers
B.
Monitoring and Controlling
C.
Planning
Answers
C.
Planning
D.
Closing
Answers
D.
Closing
Suggested answer: C