Question 402 - CAPM discussion
Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
A.
Initiating
B.
Monitoring and Controlling
C.
Planning
D.
Closing