Question 403 - CAPM discussion
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed.
What is the cost variance?
A.
-700
B.
-200
C.
200
D.
500