Question 415 - CAPM discussion
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
A.
The influence of the stakeholders increases, the cost of changes increases.
B.
The influence of the stakeholders decreases, the cost of changes increases.
C.
The influence of the stakeholders increases, the cost of changes decreases.
D.
The influence of the stakeholders decreases, the cost of changes decreases.